    some of my task do not have the correct duration calculated not all of them does anyone know what is causing this?

    #416208 Reply
    Larry Christofaro
    Larry Christofaro
    Participant
    • Expert
    • Forum Pro
    • Ombud

    Hi Bill, that can be due to calendar changes. Are you using multiple calendars for tasks/resources?

    #416398 Reply

    Do you have resources assigned to summary tasks? They should only be assigned tot he lowest levels.