Home Forums Discussion Projects

This topic contains 2 replies, has 3 voices, and was last updated by  Bruce Hayes 1 month, 2 weeks ago.

Viewing 3 posts - 1 through 3 (of 3 total)
  • Author
    Posts
  • #416206 Reply

    some of my task do not have the correct duration calculated not all of them does anyone know what is causing this?

    #416208 Reply
    Larry Christofaro
    Larry Christofaro
    Participant
    • Expert
    • Forum Pro
    • Ombud

    Hi Bill, that can be due to calendar changes. Are you using multiple calendars for tasks/resources?

    #416398 Reply

    Do you have resources assigned to summary tasks? They should only be assigned tot he lowest levels.

Viewing 3 posts - 1 through 3 (of 3 total)
Reply To: Projects
Your information:




+ 1 = 3