Loading...
Quick Links

PWA field % Complete – how does it compute?

Home Forums Discussion PWA field % Complete – how does it compute?

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #5171 Reply
    Community
    Keymaster

    Can anyone tell me how the % Complete field computes in PWA?  For example, I have a project for the which Work = 69h, AW = 61h, RW = 9h but in Project Center the % Complete field shows 28%.  I know adjusting the Work , Actual Work and Remaining Work adjusts this figure but it looks to me as though it takes some aspect of the schedule into account also.  Thx!

    #6865 Reply
    Community
    Keymaster

    Jane,Great question. % Complete is a product of duration, and % Work Complete is a product of effort. That’s the short version. Try looking at % Work Complete and you should see what you are looking for. Hope that helps…

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: PWA field % Complete – how does it compute?
Your information:




47 − = 38