PWA field % Complete – how does it compute?

Home Forums Discussion Forum PWA field % Complete – how does it compute?

Viewing 1 reply thread
  • Author
    Posts
    • #5171
      Deonne Schoner
      Keymaster

      Can anyone tell me how the % Complete field computes in PWA?  For example, I have a project for the which Work = 69h, AW = 61h, RW = 9h but in Project Center the % Complete field shows 28%.  I know adjusting the Work , Actual Work and Remaining Work adjusts this figure but it looks to me as though it takes some aspect of the schedule into account also.  Thx!

    • #6865
      Deonne Schoner
      Keymaster

      Jane,Great question. % Complete is a product of duration, and % Work Complete is a product of effort. That’s the short version. Try looking at % Work Complete and you should see what you are looking for. Hope that helps…