I am trying to find a way to create a recurring task, for project management (2 * 1/2d per week), that start at the beginning of the project and end at the end of the project, and automatically create new instance if the project end date is moved.
I tried to see if a hamock task would work but it didn’t. There isn’t a way to extend a recurring task as you are asking below. You can extend a detail task to the end of the project or change the end date of a recurring task which will automatically add recurring entries.
You can do this. First, create a project management task without any predecessor or successor set. Second, copy the Start date of the 1st task in your schedule and paste special as link to the Start date of the project management task. Third, copy the Finish date of the last task in your schedule and paste special as link to the Finish date of the project management task
Result – When the duration of tasks in the project changes, this will get reflected in project management Start, Finish and its duration.