Home › Forums › Discussion › Removing Completed Tasks
Tagged: Microsoft Project 2010, PWA
I have an issue with PWA 2010. I have multiple tasks that are completed (100% complete with 0 remaining Hours). These tasks have been approved by the Project Manager (status manager), but still show in My tasks view on PWA.
How can I get these tasks removed?
Hi,
In the ribbon set the filter to All Incomplete tasks. This is a better process to either chaning the booking type to proposed or setting the task publish field to No.
BR, Ben.
Occasionally PWA it may be useful to review recent history, such as when discussing a weekly (or daily) status review. That would be a good application for including the “completed tasks”, but again, a time-period filter should be applied to cover only those tasks completed since the last review, to avoid clutter.
Hi,
In the ribbon set the filter to All Incomplete tasks. This is a better process to either chaning the booking type to proposed or setting the task publish field to No.
BR, Ben.
“