Loading...
Quick Links

Resource Allocation –

Home Forums Discussion Resource Allocation –

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #5183 Reply
    Community
    Keymaster

    Do you allocate a resource to a milestone task. I am trying to do EVMS in MS Project 2010.

    #9863 Reply
    Community
    Keymaster

    Milestones are zero duration tasks that signal the completion of a major event (or start of one).

    So, no, you do not allocate resources to milestones – there is no work for any resource to do. If you are trying to say some special meeting (that has some duration on a specific day) is a milestone, that is not a true milestone. What you would do is list the meeting itself as a task with durations, dependencies and resources – then set a milestone (no duration, no resources) as “Customer Meeting Held”, for example.

    Roy

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: Resource Allocation –
Your information:




46 − 38 =