Loading...
Quick Links

Report on the combined status of multiple projects

Home Forums Discussion Report on the combined status of multiple projects

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #5308 Reply
    Community
    Keymaster

    What is an easy way to report on the combined status of multiple projects that have the same design?

     

    The files could be set-up as a master with subprojects.

     

    The projects have the same tasks and outline.

    #7092 Reply
    Community
    Keymaster

    If you combine them into a Master project (be cautious of the links) you could consider showing the Project Summary task (in tools/ options in 2003 /07). Another option to consider is grouping by project – there is a column that displays project name.

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: Report on the combined status of multiple projects
Your information:




− 1 = 1