Loading...
Quick Links

Report that shows unlinked tasks and other problems

Home Forums Discussion Report that shows unlinked tasks and other problems

Viewing 6 posts - 1 through 6 (of 6 total)
  • Author
    Posts
  • #4978 Reply
    Community
    Keymaster

    Hi All,
    A person that used to use Primavera and now uses Project 2003 asked me is there a report in Project 2003/2007 that shows unlinked tasks and other “work to be done” so to speak. I did show them how to add the Successors column and filter for blanks row ( as all tasks should have a successor I think) but they want a report which prints out.
    Just wondering if there is an add on etc
    Thanks
    Bert

    #6402 Reply
    Community
    Keymaster
    I would suggest that after they add Predecessors/Successors columns and filter as desired, they may execute: File/Print…
    Sorry to sound sarcastic, but that is probably the straight forward solution.
    Jim
    #3721 Reply
    Community
    Keymaster
    There are some other filters that may be of interest… Unstarted Tasks, and UnFinshed Tasks.  Remember there basic rules.
    1. There shall be no tasks with a start date left of the status date that are 0% Complete or lack an Actual Start
    2. There shall be no tasks with a finish date to the left of the status date that are not 100% complete with an Actual Finish Date.
    3. There shall be no task with a start date to the right of the status date with a %complete different from 0.
    4. There shall be no finished task with a finish date to the right of the status date.
    There are filters (or at least you can create your own) that will do all of this.
    #6403 Reply
    Community
    Keymaster
    Thanks Jim
    #6408 Reply
    Community
    Keymaster
    Hi Bert,
    I would suggest to use Reporting Services. To create such a report takes me half a day and you generate the output in Excel, PDF, Word, HTML, …format. You can make subscriptions to deliver these reports by email.
    Reporting Services makes a huge difference in the acceptance of EPM.
    Regards,
    Leo Stigter
    Head EPM Competence Centre Capgemini
    #6515 Reply
    Community
    Keymaster

    I use the MS Project auditor add-in available for $30 at qpmusa.com/QSA-Schedule-Auditor.html for terrific results that show not only missing predecessors and successors, but many other structural problems in your schedule.

Viewing 6 posts - 1 through 6 (of 6 total)
Reply To: Report that shows unlinked tasks and other problems
Your information:




− 2 = 1