Resource allocation impacts the Schedule data

Home Forums Discussion Forum Resource allocation impacts the Schedule data

Viewing 1 reply thread
  • Author
    Posts
    • #5122
      Robert Thomas
      Keymaster

      We are using MSP as a scheduling tool to plan the demand and resource fulfillment. Where we customized the tool and created our own set of columns. We log the demand with the scheduling data (day’s/week)for each role (as a task), and then allocate the resource name to the role when he/she is confirmed for the role. Where the allocation of resource should not impact the Role Scheduling part and this is how the tool was working for long time but recently we are experiencing a change the Scheduling part when we change the resource name. Hence I am looking for a solution to get out of this situation where we should get impact for the schedule data with change in the resource name. Note: 1. Resource names are from the Project Server. 2. We are not sure if there are any setting changed in recent times. Please let me know if you have any questions. Appreciate your support! Thanks Ramesh

    • #10536
      Robert Thomas
      Keymaster

      Ramesh:

      One possible impact when assigning/changing the Resource Name is that the new resource may have a different Resource Calendar.

       

      Roy