  • #20129 Reply
    Tonya De Groot
    Participant

    Is there a known reason why planned work hours in the Resource Availability graph would NOT match the planned hours in the Resource Assignments view? This is with Project Server 2010. The schedule has been published. I have gotten this on more than one occasion. Any help with this would be greatly appreciated. Thank-you!