Home Forums Discussion Resource calendar issues on Project professional

This topic contains 4 replies, has 2 voices, and was last updated by  scott gillan 2 weeks, 5 days ago.

Viewing 5 posts - 1 through 5 (of 5 total)
  • Author
    Posts
  • #416703 Reply

    Scott

    When selecting resources I lose a day over the allocated duration. It shows day one as 0.63 and the last day 0.37 equating to a full day lost. How can I remedy this? I have checked the calendars and from what I can see both the project and resource ones match.

    Thanks

    #416705 Reply
    Larry Christofaro
    Larry Christofaro
    Participant
    • Expert
    • Forum Pro
    • Ombud

    Scott, I would suggest looking at two things. 1. Go to Options / General tab and set the Date format to include the time. 2. Look at the Options / Schedule tab and make sure that the Calendar options settings, specifically Hours per day matches the calendar. Hopefully that can help diagnose the issue.

    #416706 Reply

    scott gillan

    Thanks, I’ll have a look and see how it goes.

    #416707 Reply
    Daryl Deffler
    Daryl Deffler
    #416730 Reply

    scott gillan

    Thank you, That’s helped a lot. I’m looking to use our project professional as a resource tracker over multiple projects, but all resources and allocated projects on the same file. Is this possible? I used a previous version of project in this way but, with the developments that have been made, I’m struggling to make this version work effectively. Thanks again for any help.

Viewing 5 posts - 1 through 5 (of 5 total)
Reply To: Resource calendar issues on Project professional
Your information:




98 − 94 =