Resource Calendars with different working hours

Home Forums Discussion Forum Resource Calendars with different working hours

Tagged: 

Viewing 3 reply threads
  • Author
    Posts
    • #85667
      James Paul
      Participant

      I have two teams with different working hours each day. One works 8hrs/day and the other team works 9hrs/day. How can I create two separate calendars with different working hours? If I change the working hours it seems to change for both the calendars. Can someone help with this?

    • #85810
      Sai Prasad
      Participant

      Hi James Paul

      It looks like you are editing the standard base calendar and this calendar is associated with both the teams.

      In Project, base calendar is a template that has the common working time and holidays. You can create a base calendar for each team. Then, associate the respective base calendar to the team members.

      First, create a base calendar for each team – if project 2003/2007, choose Tools, Change working time, if project 2010/2013, choose Project tab, change working time. Change the working time using work weeks.

      Next, change the view to resource sheet. Add the team member details. Double click the resource, and select change working time. Now, select the appropriate base calendar from which the working time should be inherited to resource calendar.

      So, if you change the base calendar working time then it will be applied to all team members associates with that base calendar.

    • #88035
      James Paul
      Participant

      Thanks Sai. That works.

    • #88141
      Sai Prasad
      Participant

      Most Welcome. Glad to hear that my response helped.

Viewing 3 reply threads
  • You must be logged in to reply to this topic.