Resource Loading – Query

Home Forums Discussion Forum Resource Loading – Query

Tagged: ,

Viewing 3 reply threads
  • Author
    Posts
    • #5218
      Velu Rajanbabu
      Keymaster

      Hi,

      Task 1 Start Date : 08/01/2012

      Resource1 is available only 50% from 08/01/2012 till 08/10/2012 and 100% thereafter.

      i need to assign resource1 to task1 as per the above availability, how do i do that, without entering Task1 in two rows ?

      Thanks,

      Venu

    • #6923
      Velu Rajanbabu
      Keymaster

      You could indicate availability using the calendar. Keep max units at 100% and reduce the available hours on his calendar from 8/day to 4/day during that time period.

    • #6925
      Velu Rajanbabu
      Keymaster

      the resource is already working 50% on TaskB during that period,

    • #9788
      Velu Rajanbabu
      Keymaster

      Ah, more information. That helps. Basically the KISS approach is to set all tasks to maximum assigned units and then use predesessors or other techniques to level the tasks. That would schedule Task-B for 1.5 days and then Task-A for the next 7 days. The net result gives you the end date from both tasks. Hope that helps.

Viewing 3 reply threads