Loading...
Quick Links

Resource pool in MSP 2010: Using old files (2003/2007 files)

Home Forums Discussion Resource pool in MSP 2010: Using old files (2003/2007 files)

Viewing 3 posts - 1 through 3 (of 3 total)
  • Author
    Posts
  • #5305 Reply
    Community
    Keymaster

    I have MSP 2003/ 2007 files (say 3 in no.s). I want to consolidate the same in to a master file using MSP 2010. I saved those files using save as ‘Project’ files option in 2010.  (I believe, that should convert these files in to 2010 version).

    However, I still get ‘ Version Mismatch ……..’ error when creating resource pool in 2010. Any alternative to convert these files ?

    Thanks in advance.

    #9641 Reply
    Community
    Keymaster

    n Project 2010, save the master file as “Microsoft Project 2007” format. Then, insert the Project 2003 and Project 2007 files into the master project. This will work as the file format of the master file is Project 2007 which is compatible with sub project’s file format.

    Hope this helps, Sai

    #9642 Reply
    Community
    Keymaster

    Thanks a lot. I installed a patch SP1. Now it’s OK..

Viewing 3 posts - 1 through 3 (of 3 total)
Reply To: Resource pool in MSP 2010: Using old files (2003/2007 files)
Your information:




− 3 = 2