Loading...
Quick Links

Resource Productivity

Home Forums Discussion Resource Productivity

Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • #248105 Reply

    If I have two resources A & B, who work for 8hrs each but the output they produce is different A can generate 20 units/day while B can do only 12, how do I show it in my plan?

    Thanks!

    #251130 Reply

    Hi

    Any thoughts on this? A typical manufacturing environment where the output of less experienced is lower than more experienced(both work for 8 hrs/day). How do we build this while planning?

    #253000 Reply

    You cannot plan and track your production program based on the number of units produced by using Project. But it is possible to achieve this based on resource’s time (that is, effort) in Project. Define the standard production rate, for example, x units per hour. And then determine your target volume, that is, the amount that you need to be produced per hour. Next define the task with the estimated duration corresponding to the target amount of production. You can also use custom fields to calculate the durations parametrically based on the standard production rate. Determine which one is the best for more accurate estimates, hours or days. Update the schedule based on how the production progress for each resource. The resource with low performance will need more time to produce the target amount, so the schedule will show delays for that resource’s schedule. In a nutshell, you can plan and track based on production time not the amount produced directly. I guess this is the simplest solution.

    #257359 Reply

    thanks! let me work on it and see!

Viewing 4 posts - 1 through 4 (of 4 total)
Reply To: Resource Productivity
Your information: