Loading...
Quick Links

Resource Summary by top-level task

Home Forums Discussion Resource Summary by top-level task

Viewing 3 posts - 1 through 3 (of 3 total)
  • Author
    Posts
  • #5055 Reply
    CommunityCommunity
    Keymaster

    Is it possible in project 2010 to produce a resource summary that shows the resource allocation as percent of the total work for each top-level task?

    #10424 Reply
    CommunityCommunity
    Keymaster

    Not out of the box, but this can be easily done using a VBA macro to add this information to a custom text field so it can be displayed agains summary tasks.

    #10425 Reply
    CommunityCommunity
    Keymaster

    I am of using the Grouping feature. Pls give a try. It is simple.

    You can group resources add your own fields to it for a custom grouping.

Viewing 3 posts - 1 through 3 (of 3 total)
Reply To: Resource Summary by top-level task
Your information: