  • #414310 Reply
    Carlos Santos
    Guest

    Hi

    What is the best and quick way to change the calendar to all resources?

    Regards,
    Carlos

    #414312 Reply
    Larry Christofaro
    Participant

    Update the project calendar, which defaults to the Standard Calendar.

    #414313 Reply
    Carlos Santos
    Guest

    Hi Larry

    Do not understand.
    I ll explain better my issue
    Have a Project with almost 1.000 tasks.
    All tasks have work resources assigned.
    Now we decide to set s new calendar to the project.
    The Project summary task changed the duration, all tasks were not affected.
    Than i realized that the calendar of all resources did not change to the Project new calendar, In the resource sheet.
    Have I to change the calendar in each resource? Or there is s quick way to do that?

    Regards,
    Carlos

    #414314 Reply
    Sai Prasad
    Participant
    • Community Leader
    • Forum Pro

    Carlos, In Resource Sheet view, change the base calendar of all the work resources to the new (base) calendar. This change will inherit the workweeks and exception of the bar calendar to the resource calendar.

    #414315 Reply
    Carlos Santos
    Guest

    Sai Prasad

    Thank you for your answer.
    You are saying to change all work resources calendar as:
    First filter resources type to work on resource sheet
    2nd in the calendar column change the calendar to the new one for all work resources.
    Is that it?

Viewing 5 posts - 1 through 5 (of 5 total)