Resources Calendar change

Home Forums Discussion Forum Resources Calendar change

Viewing 2 reply threads
  • Author
    Posts
    • #414310
      Carlos Santos
      Guest

      Hi

      What is the best and quick way to change the calendar to all resources?

      Regards,
      Carlos

    • #414312
      Larry Christofaro
      Participant

      Update the project calendar, which defaults to the Standard Calendar.

      • #414313
        Carlos Santos
        Guest

        Hi Larry

        Do not understand.
        I ll explain better my issue
        Have a Project with almost 1.000 tasks.
        All tasks have work resources assigned.
        Now we decide to set s new calendar to the project.
        The Project summary task changed the duration, all tasks were not affected.
        Than i realized that the calendar of all resources did not change to the Project new calendar, In the resource sheet.
        Have I to change the calendar in each resource? Or there is s quick way to do that?

        Regards,
        Carlos

    • #414314
      Sai Prasad
      Participant

      Carlos, In Resource Sheet view, change the base calendar of all the work resources to the new (base) calendar. This change will inherit the workweeks and exception of the bar calendar to the resource calendar.

      • #414315
        Carlos Santos
        Guest

        Sai Prasad

        Thank you for your answer.
        You are saying to change all work resources calendar as:
        First filter resources type to work on resource sheet
        2nd in the calendar column change the calendar to the new one for all work resources.
        Is that it?

Viewing 2 reply threads
  • You must be logged in to reply to this topic.