In MS Project 2016, is it possible to restrict execution of tasks to date ranges? E.g. certain tasks cannot be performed between two dates?
Pat; While I’ve never had to do this, I would suggest trying a task specific calendar. Since your request is for the task to NOT be worked on between certain dates, you can make those days non-working days in the task calendar. Hope that helps
Thanks Daryl, I’ll give it a try