    In MS/Project how can you associate risks and issues with a specific task; ie. if a specific risk requires that we employ risk mitigation activities that involve time and effort it gets reflectsed in the project schedule.
    Charles Fraley
    #6161 Reply
    Community
    Keymaster
    Hi Charles,
    Project Server has a link to tasks for both Risks and Issues.
    If your using Project Standard then maybe you should use a custom field to indicate the Risk ID from your register. You could then Filter and Group on that field to see the effort/cost for the mitigation activities by Risk.
    Simon Newton