Loading...
Quick Links

Schedule Challenge…! Show others how to create a schedule Totem Pole Chart to depict Current vs BL Total Slack within MSP

Home Forums Discussion Schedule Challenge…! Show others how to create a schedule Totem Pole Chart to depict Current vs BL Total Slack within MSP

Viewing 5 posts - 1 through 5 (of 5 total)
  • Author
    Posts
  • #2200 Reply
    Community
    Keymaster

    Here’s a Schedule Challenge… at the conference!  Show others how to create a schedule Totem Pole Chart to depict Current vs BL Total Slack within MSP.

    There should be a Microsoft Office Project “Challenge” Workshop for various people to demonstrate unusual views and reports generated from Project.  It should be modereated by Microsoft and othere professional experts!

     

    Regards;

    Angelo

    #6632 Reply
    Community
    Keymaster

    Hi, Angelo – could you explain more what you mean by Totem Pole Chart.  Thanks.

    #10389 Reply
    Community
    Keymaster

    A Totem Chart graphically depicts, in the gantt chart area, the amount of slack key tasks have when baselined, and compares that to TS at any point.  Timescale is labled from a 0 axis, as M-1, M-2, M-3 … for positive slack and -M-1, -M-2, -M-3 … for negative slack.  Bars are black for baseline slack, green for current positive slack and red for current negitive slack.  I will e-mail you a pic.

    #10390 Reply
    Community
    Keymaster

    Please mail a picture to me as well.  This is a tool (visually displaying slack) that I need and have not found any good tools to date.  My AOL address is SteveRuger.

     

    Thanks.

    #10391 Reply
    Community
    Keymaster

    Please mail the totem pole example picture to me, too. My address is cgood@csc.com

Viewing 5 posts - 1 through 5 (of 5 total)
Reply To: Schedule Challenge…! Show others how to create a schedule Totem Pole Chart to depict Current vs BL Total Slack within MSP
Your information:




84 + = 85