Scheduling equipment as resource

Home Forums Discussion Scheduling equipment as resource

Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • #6491 Reply
    CommunityCommunity
    Keymaster
    Kerstin —
    Since Microsoft Project 2010 does not include a formal type of resource called an Equipment resource, about the only thing you can do is to go to Resource > Leveling Options and DESELECT the Leveling Can Create Splits in Remaining Work option and DESELECT the Leveling Can Adjust Individual Assignments on a Task option.  Hope this helps.
    #5021 Reply
    CommunityCommunity
    Keymaster

    Hi-

    I was wondering if anyone knew of an easy way to schedule equipment as a resource so the task doesn’t break.  Even when scheduling to available date, it will break the task.  I need it to stay the entire duration because the activity requires special laboratory equipment.  Any ideas would be greatly appreciated!  So far I have been manually dragging the other end of the task back to attach it.

    #6519 Reply
    CommunityCommunity
    Keymaster
    Kerstin,
    I suggest editing the equipment resource to use the built-in 24 hour calendar (or create a renamed copy if you need to include exceptions) instead of the standard project calendar.
    #6520 Reply
    CommunityCommunity
    Keymaster
    Kerstin,
    I suggest editing the equipment resource to use the built-in 24 hour calendar (or create a renamed copy if you need to include exceptions) instead of the standard project calendar.
Viewing 4 posts - 1 through 4 (of 4 total)