Show Holidays on Gantt Chart Project 2010

Home Forums Discussion Show Holidays on Gantt Chart Project 2010

Viewing 6 posts - 1 through 6 (of 6 total)
  • Author
    Posts
  • #160937 Reply
    Alasdair
    Guest

    Wondering if anyone has had a requirement to show holidays on the Gantt Chart in Project 2010? Is it possible to show holidays with the resource name alongside and show the task also with their name alongside. Creating a separate task for holidays is a work around, but though there should be a better way? Can anyone help?

    #165066 Reply
    Sabina
    Guest

    I too have this question. If I am using Enterprise calendars for each person to show their holidays, how can I then see whole teams of people and when they are on holiday? I don’t want to set up a dummy project for holidays as that would still allow people to book resources that are on holiday in other projects.

    #196037 Reply
    Lavinia Lung
    Guest

    I found this add in, which can produce you a new report based on resources calendar. You can see the screenshots.
    Let me know if this helped you!

    #196123 Reply

    Lavinia,

    You can use this one for free:
    Representing Non-Working Time as Tasks in Microsoft Project by Jan De Messemaeker (MVP)
    http://users.online.be/prom-ade/project_en.htm

    Regards,
    Ismet

    #196230 Reply

    Lavinia, I presume you are Marketing Project Manager for Power2Plan. So I guess you are the right address to ask for “Why don’t you offer free trial ?”. Regards, Ismet

    #206219 Reply
    Lavinia Lung
    Guest

    Hi Ismet, that’s right. I’m the Marketing Project Manager. We do have a trial, sorry that I didn’t reply to you earlier. I’ll be happy to try it and give an opinion about it. 🙂 Regards, Lavinia

Viewing 6 posts - 1 through 6 (of 6 total)