Simulation Tools for MS Project

Home Forums Discussion Forum Simulation Tools for MS Project

Viewing 2 reply threads
  • Author
    Posts
    • #5119
      Robert Thomas
      Keymaster

      Does anyone have a recommendation for a really good, intuitive simulator for MS Project?  Looking for something that can take a project schedule, and do pre-programmed what if simulations on schedule executions.

       

      Thanks!

       

      Russ

    • #6782
      Robert Thomas
      Keymaster

      You are not the first person to ask for this however since each person has a different idea of what the simulation should be.  I doubt you will find what you are looking for.

      One client I am working with wants a what-if that is more crashing the schedule and it would have to be adjustments to selective tasks.  Another one tells me that want to get a what-if on if they have endless resources.  Someone else I know wants what’ifs on increasing all resource availability by 1 hr per day.

      What i would do is take a copy of the schedule, set a baseline into baseline1 to get the picture of what you started with.  Then make all of the changes you need.  Then set the baseline into baseline 0.  Look at the Multiple Baseline Gantt and see the difference.

      Ellen Lehnert, MVP, PMP

       

    • #6788
      Robert Thomas
      Keymaster

      If you are looking for Monte Carlo simulation than the two products I would try out are @Risk by Palisade Software and Full Monte by Barbecana.  Otherwise I don’t know of a tool that you can state criteria and have Project schedule accordingly.