Home Forums Customization SS and FF relation to the same task?

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #345978 Reply
    Nadim Daou
    Member

    How’s a task can be structured in MS Project 2010 where a predecessor and successor relationship reference to the same task, i.e. when the task-B needs to start SS (with or without lags) Task-A , and needs to FF (with lags or wuithout lags) Task-A (same predecessor task) – which means MS Project to automatically adjust the duration of Task-B when Task-A duration/dates change.
    Appreciate your replies.

    #349035 Reply
    Sai Prasad
    Participant
    • Community Leader
    • Forum Pro

    Hi – In Project, you can’t set two dependency types between the same predecessor and successor. Alternate is have SS dependency and revise the duration of the successor every time the predecessor duration changes. Another alternative is don’t any dependency between A and B rather copy the start date of task A and paste it as link in Task B star column and do the same for finish date. For more information, visit https://support.microsoft.com/en-us/kb/141733

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: SS and FF relation to the same task?
Your information:




39 − = 33