Start and Finish Columns

Home Forums Discussion Start and Finish Columns

This topic contains 3 replies, has 2 voices, and was last updated by  Varun Kumar Gupta PMP 2 weeks, 6 days ago.

Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • #472394 Reply

    1. What is the difference between Start and Scheduled Start and Finish and Scheduled Finish ? Which one should be displayed in my schedule ?
    2. There are blank rows in the resource sheet of my schedule. Should they be deleted ? Can we find them in a single click as sorting the resource by ID I found there are 1756 resources in the schedule I need to correct
    3. Is there a way to find out duplicate tasks and resources in my schedule with a formula in Graphical Indicators or so ?

    With Best Regards,
    Varun.K.Gupta

    #472418 Reply
    Daryl Deffler
    Daryl Deffler

    Varun;
    For #1.
    Most of the time both sets of fields are the same. But there is a slight difference between MS Project scheduled tasks as Manually scheduled tasks.
    Auto Scheduled Tasks: Scheduled Start/Finish reflects the date calculated by Projects scheduling algorithm. Start/Finish will show the same date.
    Manually Scheduled Tasks: Scheduled fields work the same, showing the dates when Project would schedule them. However, Start/Finish show the manual start/finish dates as entered by the PM.
    As for which to display, Start/Finish will always show what the schedule shows and I would suggest using these.
    Also, for future reference, here’s a good place to find field definitions. I’m sure there are probably others as well.
    https://www.projectplan365.com/articles/project-fields/

    Hope that helps.

    #472426 Reply

    Thank you Sir

    #472547 Reply

    And before putting percent complete, do we set a baseline first always. Is it compulsory ?

Viewing 4 posts - 1 through 4 (of 4 total)