Loading...
Quick Links

start time many years ago

Home Forums Discussion start time many years ago

Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • #179143 Reply
    pasquale colonna
    Guest

    it is possible to input many years ago as start time (historical pert)?

    #179184 Reply

    Yes, use Move Project command for an existing project plan file in a plan with no actuals.

    #181166 Reply
    pasquale colonna
    Guest

    thanks! I will try to do so.

    #182445 Reply
    pasquale colonna
    Guest

    Unfortunately the problem is not solved, because the minimum start time for the software is 01/01/1984, but the date to enter is thousands of years before Christ!! Does anyone know a solution to force the earlist starting date?

Viewing 4 posts - 1 through 4 (of 4 total)
Reply To: Reply #179184 in start time many years ago
Your information:




88 + = 97