Home › Forums › Discussion Forum › Status bar problem.
Tagged: Microsoft Project 2003
Can anyone tell me why my status bar is not coming up to the status date line? I have it scheduled as on track using the status icon. using MSP 2003 still, SP-3. The problem is the selected tasks do not look as if they are on track. I don’t want to do it universally, just selected ones.
Hi – is the progress bar not reaching the time-now status line or is it sliding past it? When this has happened to me before, it was due to a day excluded Friday from the calendar like a holiday and looks like the task progress stopped on Thursday. Or I’ve had the progress bar slip into the next Monday. Make sure you’re working time in the calendar ends at 5:00pm. I have had that issue with tasks using odd calendars like second shift or 24hr calendars. Hope you can resolve it.
Steve,
Thanks but it’s not a calendar proble. I found a workaround (sort of). If I delete duration and % then re-insert them it solves the problem, I just was looking for a root cause but I think it’s just one of those things!