Subplanning within masterplan gives wrong end-date

Home Forums Discussion Forum Subplanning within masterplan gives wrong end-date

Viewing 2 reply threads
  • Author
    Posts
    • #4839
      Shaik karima
      Keymaster
      Dear all,
      I did some research but could not find the answer. I made a masterplan with some subplans in it (a projectplan with inserted projects).One of those subprojects is changing his end date by itself. When opening (collapsing) the plan it switch immediately to the right end date. Which, in my opinion, is weird. I searched what could go ‘wrong’ in te subproject but could’t find any.

      How’s this possible?

      Thanks in advance.
    • #6024
      Shaik karima
      Keymaster

      Depending on how you set up the Master Shell, you may have inadvertently used a "new" file with a start date in the future, compared to the subprojects; You then may have linked a task wing the Master Shell which caused the end-date to shift to the right.

      Hope this helps…

      Angelo Arcoleo, PMP

    • #6081
      Shaik karima
      Keymaster
      Make certain the calendars match in the projects. If the master uses a standard (default) calendar and so do the subprojects, then also verify the standard calendar has not been modified in the subproject files.
      A common error is to modify the standard calendar with company holidays, etc.
      -Jim Aksel