Subset of data in a MS Project 2016

Home Forums Discussion Forum Subset of data in a MS Project 2016

Viewing 6 reply threads
  • Author
    Posts
    • #414668
      Chris Waller
      Guest

      Hi,

      A colleague of mine has a very complex MS Project. What he wants to know is, is it possible to create a subset of some of the data in another project and somehow link the two so if the dates change in one of the projects it updates the dates automatically in the other project?
      If anyone knows if this is possible I would appreciate clear instructions as I am not a whiz on Project neither is my colleague.
      TIA

    • #414669
      Jigs Gaton
      Member

      Chris, just do what you can to learn about Master Projects and Sub Projects (it’s in the interface). Basically, you create a master plan, imbed the subsets, and then use the master plan or any of the subprojects to change the data, and then data is automatically updated in both places (master and sub). It’s really easy but the only caveat is that you don’t want to move file locations after you set things up. Links are created, and while they can be broken / changed, it’s not intuitive. Also, hosting linked .MPP files on cloud services (with bad / iffy connectivity) can also be problematic. Just a few thoughts – best, Jigs

    • #414670
      Chris Waller
      Guest

      Jigs,

      Thanks for the prompt response. I will try to learn about Master Projects and Sub Projects. I cannot pretend that I know how this works, but I will work on it

    • #414672
      Jigs Gaton
      Member

      @chris sure thing, and it is not complex, u (or ur pal) just have to learn the clicks to imbed sub project(s), and off u go. You may be familiar with the concept in Microsoft Word (called Master Document). Under View / Outline / Master Document in MS Word, you are doing essentially the same thing in MS Project under Project / Subproject. Good luck!

    • #414674
      stein milward
      Guest

      Chris
      It’s like Jigs says, very straight forward. The only difference is that you use the CTRL key to select tasks in the subprojects to link tasks.

      BR
      Stein Milward
      Kurs og planlegging
      http://www.msproject.no

    • #414675
      stein milward
      Guest

      Chris

      One thing about master and subprojects. Never ever involve summary tasks in your link’s, that can cause MASSIVE corruption of the master project. Always link task’s to other task’s – never link to or from summary tasks!!!

      BR
      Stein Milward
      Kurs og planlegging
      https://www.msproject.no

    • #414688
      Chris Waller
      Guest

      Stein,
      Thanks for your post yesterday. I wonder if you could expand on what you were saying about using the CTRL key to select tasks in the subprojects to link tasks.