Loading...
Quick Links

Summary Tasks with external dependencies

Home Forums Discussion Summary Tasks with external dependencies

Viewing 3 posts - 1 through 3 (of 3 total)
  • Author
    Posts
  • #5246 Reply
    CommunityCommunity
    Keymaster

    I understand that Summary Task must not have any links. but the scenario is as follows:

     

    Can I have the summary task in this file as an external predecessor to a task in another file to capture the start and end dates? Will this create any issues?

    Thanks

    #6977 Reply
    CommunityCommunity
    Keymaster

    I would link with task 3 since all your tasks are waterfall..

    #9723 Reply
    CommunityCommunity
    Keymaster

    To stay with best practices for scheduling, I agree. You need to connect to a task and since Task 3 is the last in your series, that would be the one to use. In other situations, you can usually create a task that serves just this purpose as well.

Viewing 3 posts - 1 through 3 (of 3 total)
Reply To: Summary Tasks with external dependencies
Your information:




+ 29 = 35