Task created after baseline set

Home Forums Discussion Task created after baseline set

Viewing 3 posts - 1 through 3 (of 3 total)
  • Author
    Posts
  • #380747 Reply
    kamlesh Parmessur
    Participant

    Hello everybody

    I have a project file where some activities were added after the baseline was set.
    In fact some of the tasks where further detailed and indented; so as it has now been made a summary task with baseline but the detailed ones does not has a baseline date.

    can i copy the baseline dates from the summary task and paste the baseline dates into the detailed tasks?

    #380749 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    Your situation is common and can be a challenge to get right. You might want to see if you can find a good blog on the subject, but here’s a short version. Select only those new tasks and any tasks dependent on those tasks, then set baseline for selected tasks and rollup to summaries. It requires a properly managed project (no deleted baselined tasks, etc.). Make sure you validate the rollup to what you would expect (total hours, total costs, etc.).

    #380765 Reply
    kamlesh Parmessur
    Participant

    Hi Larry

    Thank you for the advice.
    I’ll try it and feedback you.

Viewing 3 posts - 1 through 3 (of 3 total)