  • #4840 Reply
    Community
    Keymaster
    Using the Task Drivers tool, I looked at a task with four predecessors.  Three of the predecessors were FS or SS, but none of them had any dates that would drive the successor task.  The FF link was the one driving the start, but the Task Drivers tool would not show that link.
    Have you seen this behavior?  Is there a fix?