Team Planner View is not available

Home Forums Discussion Team Planner View is not available

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #412857 Reply
    Eduardo Torres
    Guest

    Hi, i have been trying to use the team planner view, but i can´t find it, i have project 2016, do you know where can i find it?

    have a good day!

    #412864 Reply
    Larry Christofaro
    Participant

    Team planner is only available in Project Professional. You won’t find it in Project Standard. Could that be the problem?