Timeline Timescale setting in Project 2013?

Home Forums Discussion Forum Timeline Timescale setting in Project 2013?

  • This topic is empty.
Viewing 4 reply threads
  • Author
    Posts
    • #66752
      Sheryl Pass
      Participant

      Does anyone know how to scale the timeline to show a specific date range?  I located a post (https://answers.microsoft.com/en-us/office/forum/office_2013_release-project/timeline-timescale-setting-in-project-2013/06e104c1-5de8-4b8a-bbdf-fa4613f0fd88?auth=1) that says:

      The Timeline shows the entire project from start to finish date – even if you don’t have tasks added to the timeline.
      I can reproduce what you report and cannot seem to find an elegant way of changing the formatting short of changing task durations and forcing a re-paint of the timeline scale.

      Am I missing something?

    • #71057
      Ismet Kocaman
      Guest

      Sheryl, No. It is not possible to change the range preset. Regards, –Ismet

    • #415873
      Ian H
      Guest

      I realise this is an old post but in case anyone else reads it and wonders:-)

      You can change the date range by clicking on the timeline date line, then going to Format > Date Range and input the range you want to show.

    • #417182
      Amanda K
      Guest

      In response to Ian’s post, the option to adjust the timescale of your timeline is only available in the Project PROFESSIONAL version, and not in Standard. I have been doing extensive research trying to make it work and have decided to just create a custom timeline in MS Excel to suit this particular need.

    • #418002
      Walid A
      Guest

      I have Project professional, and I am able to set the date range for a specific timeline. The problem is that I can only do that for the first time. It doesn’t allow me to change the date range a second time for the same timeline (the button is grayed).it seems it’s one-time change that cannot be edited again. Anyone know the solution?