Loading...
Quick Links

Timeline Web Part in Project Online

Home Forums Discussion Timeline Web Part in Project Online

Viewing 3 posts - 1 through 3 (of 3 total)
  • Author
    Posts
  • #363247 Reply
    Jim Walsh
    Member

    I am trying to create a project center page for each facility in our solution.

    I created the page to contain the Timeline web part and the Project Center web part, and wanted each page to display a different view based on location/facility.

    Likewise, I want the Timeline web part to be reactive to the Project Center view filter so only projects from facility ‘A’ show on the timeline page for that facility.

    Unfortunatelty I do not think this is possible by what I’ve tested thus far.

    Has anyone successfullt been able to create a Timeline Web part that is independent of the Instance?

    #363263 Reply
    Larry Christofaro
    Participant

    Unfortunately it doesn’t work like that in Project Server 2010 or 2013. Improvements are coming in Project Server 2016 which might help but it isn’t out yet so will need to wait and see.

    #363320 Reply
    Jim Walsh
    Guest

    Larry:
    Thanks for saving me time in chasing this down. It’s always ‘the next release’ isn’t it?
    Jim

Viewing 3 posts - 1 through 3 (of 3 total)
Reply To: Reply #363263 in Timeline Web Part in Project Online
Your information:




46 − 42 =