Does anyone know if there are add on tools which can take data from MS Project and generate an S-Curve to track schedule performance and schedule forecast? Specifically, track and calculate schedule variances using actual start, actual finish versus baseline start and baseline finish dates. Additionally, track number of actual “inch-stones” completed against baseline and all actual “inch-stones” completed. In this context “inch-stones” refers to each actual start and actual finish in a schedule.
Hello Paul,
http://www.ProjectProCorp.com. offers an S Curve Add In tool. Give it a try they offer a Trail edition.
Regards,
Matt