Total for Work Hours in summary doesn't match sum of work hours for tasks

Home Forums Discussion Total for Work Hours in summary doesn't match sum of work hours for tasks

Viewing 5 posts - 1 through 5 (of 5 total)
  • Author
    Posts
  • #412808 Reply

    Hi All,
    I have a project that I’m managing as a fixed work. Resource availability varies daily as we share our project team with ops. Once I enter the work for each subtask, I notice that the sum of all the work in the under a summary doesn’t match the total of work listed for the summary. Is this normal?

    Thanks
    Mark

    Deploy to Val 81 hrs
    Submit Request for Data Export & Import for Val Lynn 1 hr
    Migrate VAL Schema Generic DBA – Oracle 1 hr
    Execute Val IQ George 1 hr
    OQ or Smoke Tests – Test Execution Generic Tester 40 hrs
    System Test Package – Test Lead Approval Test Lead 2 hrs
    System Test Package – Compliance Approval Compliance 8 hrs
    Execute PQ (UAT) in Val Generic Customer 16 hrs

    #412809 Reply
    Larry Christofaro
    Participant

    Mark, it’s hard to tell with what you show because it isn’t an actual Project view. First thing to check is, do you have anyone assigned to the summary task?

    #412810 Reply

    Hi Larry,
    I have no one assigned to the summary. I just created a brand new project file, and listed three tasks under a summary. The tasks total 6 hours… but the summary shows 0. I’m starting to believe I have an issue with my install of project.

    Thanks,
    Mark

    #412811 Reply

    Okay… I feel stupid. I had somehow, accidentally, turned auto-calc off.
    Thanks a bunch…
    Mark

    #412812 Reply
    Larry Christofaro
    Participant

    No worries, glad it’s working…!