Tracking Progress tasks with costs and work resources assigned / PV (BCWS) VALUE

Home Forums Discussion Tracking Progress tasks with costs and work resources assigned / PV (BCWS) VALUE

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #414289 Reply
    Carlos Santos
    Guest

    Hi

    I have a Project with more than 300 tasks.
    I made the “mistake” assigned both, costs and work resources, to each task.
    I said “made mistake” because when tracking progress I realized that the costs resources were not updated. I had to manually update the costs in the Task Usage View (tracking table, actual cost field/column).This is how MS Project works. Ok. Next time is better add tasks with only costs resources.
    My question/Issue is: After Tracking, in the Earned Value Table, the value PV(BCWS) IS ALSO NOT UPDATED. This field I can do nothing!
    Solution?

    Regards,
    Carlos

    #414290 Reply
    Carlos Santos
    Guest

    Not only the PV (BCWS) value, the AC (ACWP) Value is also not updated.