Unit value not calculate automatically for fix duration task type when work value change

Home Forums Discussion Forum Unit value not calculate automatically for fix duration task type when work value change

Viewing 1 reply thread
  • Author
    Posts
    • #4837
      Preeti Dimble
      Keymaster

      I have tried the following on Project Professional 2010 and noticed that Project 2010 did not adjust the unit as expected. Example: Fix duration task require 10 days to complete with 1 resource assigned. Work value change automatically to 80h and unit value stay at 1 (Assignment Unit = “Decimal”) immediately after resource assignment. However, if I were to change the work value to 40h, the unit value remains at 1. Wondering if anyone encountered such situation? KG Project Professional 2010 version : 14.0.4760.1000 (32-bits)

    • #6017
      Preeti Dimble
      Keymaster
      Project 2010 changes the way this works. Its noe Peak Units that changes. See blogs.msdn.com/b/project/archive/2010/04/29/assignment-units-in-project-2010.aspx
      Kevin Watson Microsoft