I have tried the following on Project Professional 2010 and noticed that Project 2010 did not adjust the unit as expected. Example: Fix duration task require 10 days to complete with 1 resource assigned. Work value change automatically to 80h and unit value stay at 1 (Assignment Unit = “Decimal”) immediately after resource assignment. However, if I were to change the work value to 40h, the unit value remains at 1. Wondering if anyone encountered such situation? KG Project Professional 2010 version : 14.0.4760.1000 (32-bits)