Update only extending, and not moving, tasks with links automatically

Home Forums Discussion Update only extending, and not moving, tasks with links automatically

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #112208 Reply
    Maurilio Rossi
    Guest

    Dear All,
    I am kind of a novice here.
    I have this issue with Ms Project since weeks now, and did not find any solution so far.
    When I create a task, and I give this task a duration, and link it to a predecessor (let’s say a milestone), I want to be able to extend automatically the task I created if I happen to move the milestone. What instead is happening is that, using the right constraints, I have been able only to MOVE the task, and not just extend it (in some cases is ok, in some others is not reality and task should extend).
    I have a schedule with 200 tasks, and each approx. 40 tasks are linked to one milestone. If I move the milestone, the dependant task should Extend and not move. Is there a setting in Ms Project I can choose where I must only to move the milestone and the dependant tasks are extended if I chose the extension, and moved If I chose to move it?

    #116215 Reply
    Sai PrasadSai Prasad
    Participant
    • Community Leader
    • Forum Pro

    When the task is delayed/extended, Project will only adjust the start date of its successor; assuming it is FS dependency. But you want the duration of the 40 tasks to expand/reduce when you move the linked milestone is moved which is not possible.

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: Update only extending, and not moving, tasks with links automatically