Variation in the duration of a task depending on predecessors and / or successor

Home Forums Discussion Variation in the duration of a task depending on predecessors and / or successor

Tagged: 

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #478979 Reply
    guy forget
    Participant

    Is there a way to make the duration of a task automatically adjust based on predecessors and / or successors. Ex: Three finish to start tasks A, B, and C. I want the duration of the task ” B ” to adjust automatically if the end of the task ”A” and / or the start of the task ” C ” change in time,

    #479183 Reply

    Guy;
    MS Project supports something called “Hammock Tasks” where the duration of one task is dependent on other tasks. I found this MPUG article which may help.
    Not sure if this is exactly what you’re looking for.

    Do’s and Don’ts: Using Hammock Tasks

    Hope this helps