Can anyone provide a resource for how to create WBS from their project schedule in Visio? I am not finding the information I’m looking for by doing a google search. It appears the functionality was taken out of 2007.
Thanks in advance!
Hi Elise —
Have you tried the Visio WBS Modeler?
http://www.microsoft.com/download/en/details.aspx?id=26229
This is a free add-in for Visio 2010 Pro or Premium that you can download and install, and one of its features allows you to open an existing project schedule and visualize its Work Breakdown Structure in Visio.
Good luck!
— tz