Home › Forums › Discussion Forum › What is with the print view horizontal lines?
Tagged: horizontal lines, Microsoft Project 2010, print, print view
Hi,
It sound as if you have Updated Project to the Status Date, thus moving uncompleted tasks or parts of tasks to start at the Status Date. The lines you are referring to show how much the tasks have been moved.
Mike Glen
Project MVP
See https://tinyurl.com/2xbhc for my free Project Tutorials