    I’m using a main project with 5 sub-projects. One of the sub-projects is a resource pool. When I try to level two tasks from different sub-projects the ‘Level Selection’ menu is disabled? Why would that be the case?

    Thanks,
    Dan

    #418498 Reply
    Daryl Deffler
    Guest

    Dan,
    Its been a while, But I believe you need to select more than one task, then select the Level Selection option. Meaning you need to make the selection before you try to click level selection.
    Hope that helps

    #418499 Reply

    Daryl,

    I wish it were that simple. I’m trying to level two tasks from different sub-projects and it’s not enabling.

    Any other ideas?

    Thanks,
    Dan

    #418533 Reply
    ben howard
    Guest

    Do either of the tasks have actual start dates? Can you post an image to show?

    #418534 Reply

    Ben,

    Nope. They’ve both got an Actual Start date = N/A. I’ve posted a screen grab here. Let me know if you can’t read it.

    Thanks,
    Dan

    #418600 Reply

    Any hints Ben?