Why the total days are in correct in summary task ?

Home Forums Discussion Forum Why the total days are in correct in summary task ?

Viewing 8 reply threads
  • Author
    Posts
    • #2194
      Besnik Himaj
      Keymaster

      Hi,

      I have been facing this issue at several times that the total number of days in the summary task are incorrect.

      For example, in project plan, there are 4 sub-groups. Group 1 has 12 days, group 2 have 18 days, group 3 has 7 days and group 4 has 25 days. The main summary task should have the total of ( 12+18+7+25) = 62 days but it is has 42.

      I checked the link of each task and each task is also linked in a sequence.

      I could not figure it out that why the total duration is incorrent. I updated my MS Project 2010 with latest patchs / updates.

      Anyone who could help me, would be highly appreciated.

      Thanks,

      Abey

    • #6610
      Besnik Himaj
      Keymaster

      If you are using manual mode the totals will not necessarily add up to the total duration.  If the tasks are in automatic and are linked FS they should add up to the total duration of each task on the summary.  However, customized fields have an option of rolling up and so do baselines.

    • #6612
      Besnik Himaj
      Keymaster

      Hi Abey —

      Looks like this may be a case where a picture is worth a thousand words. Can you include a screenshot of your gantt chart?

      — tz

       

    • #6700
      Besnik Himaj
      Keymaster

      If one or more tasks has a calendar assigned to it that is different from the Project calendar, you will get resluts such as you describe.  For example, using your data I assigned the Standard calendar to the project and a 24-hour calendar to the first two groups.  My project duration now is 39 days instead of 62.

      Things like this can also happen under certain circumstances if a resource assigned to a task has a calendar other than the Project calendar.

    • #10548
      Besnik Himaj
      Keymaster

      It is not necessary that they will add up.It depends on your linking.

      I think you are using FS dependency. However, if your group tasks are not linked in FS way, then it will not add up.

      Yes, please give a snap for TaskSheet view of the project.

    • #10549
      Besnik Himaj
      Keymaster

      Days in the sumamry line (I don’t like calling them tasks because they are not actually a task) are not additive.  It is the working days between the earliest start date of any task in the sub-group and the latest finish date of any task in the sub-group.  If for example there are 10 tasks in the group of 10 days each that all start on the same day and all finish on the same day, the total days will be 10, not 100.

      Roll up groups above indented groups follow the same logic.

    • #517643
      WalterReeves
      Participant

      I tried to figure it out and after spending a lot of time I couldn’t. The only place I could find a solution was by asking to write my assignment. In my opinion it is better to assign some tasks to experts. This saves time for more important tasks.

    • #517748
      aemoutsource
      Participant

      Days in the sumamry line (I could do without calling them undertakings since they are not really an assignment) are not added substance. It is the functioning days between the earliest beginning date of any errand in the sub-bunch and the most recent completion date of any assignment in the sub-bunch.
      Thanks.
      AEM Developers in India

    • #523354
      tear lemon
      Guest

      Friday Night Funkin is a PC game that will challenge the price of your rhythm. The game will ask you to press a button at a specific time: the screen will tell you which button to press and the game will show you both the rhythm accuracy and the time.

Viewing 8 reply threads
  • You must be logged in to reply to this topic.