Loading...
Quick Links

wiped out duration

Home Forums Discussion wiped out duration

Viewing 5 posts - 1 through 5 (of 5 total)
  • Author
    Posts
  • #404093 Reply

    Having difficulty pinpointing what is causing a mass change to durations and making tasks milestones that have already been completed months ago. This occurred throughout multiple functional areas, phases throughout the project and across resources. It appears that adding a resource to a task in Work under Details in Gantt view triggers it. Why would this be a trigger?

    #404095 Reply

    I don’t have a solution, but here’s some questions that may help others…
    What version (and CU if known) of Project is this occurring on?
    Are you using resource assignments on summary tasks?
    Are the disappearing hours only on tasks, or do they disappear on resources assigned to summary tasks also?
    Specifically, when you add the resource…
    Are you adding the resource to a task or a summary task?
    Is the resource an enterprise resource or local resource?

    #404096 Reply

    MS Project 2013 Pro
    no resource assignments on summary tasks
    hours disappear on tasks AND the resources assigned to tasks
    local resource

    #404103 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    Sorry Anna, I don’t have a solution either. It doesn’t work that way and I can’t think of any scenario that would do that. One more question, is it happening on just one project? If so it might be some corruption in that project. If updates have all been applied I don’t know what else I can suggest. Sorry about that…

    #404202 Reply
    Sai PrasadSai Prasad
    Participant
    • Community Leader
    • Forum Pro

    Anna – Did you try recreating this issue a new blank project?

Viewing 5 posts - 1 through 5 (of 5 total)
Reply To: wiped out duration
Your information: