wiped out duration

Home Forums Discussion Forum wiped out duration

Viewing 4 reply threads
  • Author
    Posts
    • #404093
      Anna Wassom
      Member

      Having difficulty pinpointing what is causing a mass change to durations and making tasks milestones that have already been completed months ago. This occurred throughout multiple functional areas, phases throughout the project and across resources. It appears that adding a resource to a task in Work under Details in Gantt view triggers it. Why would this be a trigger?

    • #404095
      Daryl Deffler
      Participant

      I don’t have a solution, but here’s some questions that may help others…
      What version (and CU if known) of Project is this occurring on?
      Are you using resource assignments on summary tasks?
      Are the disappearing hours only on tasks, or do they disappear on resources assigned to summary tasks also?
      Specifically, when you add the resource…
      Are you adding the resource to a task or a summary task?
      Is the resource an enterprise resource or local resource?

    • #404096
      Anna Wassom
      Member

      MS Project 2013 Pro
      no resource assignments on summary tasks
      hours disappear on tasks AND the resources assigned to tasks
      local resource

    • #404103
      Larry Christofaro
      Participant

      Sorry Anna, I don’t have a solution either. It doesn’t work that way and I can’t think of any scenario that would do that. One more question, is it happening on just one project? If so it might be some corruption in that project. If updates have all been applied I don’t know what else I can suggest. Sorry about that…

    • #404202
      Sai Prasad
      Participant

      Anna – Did you try recreating this issue a new blank project?

Viewing 4 reply threads
  • You must be logged in to reply to this topic.