This is the second article of this series highlighting common incorrect uses of Microsoft Project. The images in these posts are built using the Microsoft Project 2013 Pro edition, but this series can be useful for all versions of the product.

Flaw #1: Date-Related Planning

Flaw #2: Capacity as Activity

This flaw is pretty self-explanatory once you see the image below:

flaw2.2

You are looking at a Gantt chart where 3 people need to work on a document. From the view, it is clear that the 3 people need to do things separately. And there’s the problem: “things” isn’t really something you can do.

Project resource planning or allocating should be done on a different level. We need to add our resources using a different view in Microsoft Project called the Resource sheet.

flaw2.3

I added Erik, Dave and John in the resource sheet. I also added some additional information like a standard hourly rate and a Base calendar.

Now we go back to our Gantt chart view to change the names of the activities and add the resources to these activities. In other words: we are generating assignments for the resources to the tasks.

I have changed the names of the 3 tasks to represent the different actions that need to be taken.

flaw2.4

Now I know what the team needs to do. And I can assign my resources appropriately. Using the details view in the views tab, I can assign Erik to “Write the first draft,” and even give a indication on how many hours he needs to work on the task. “Work” is a column I can add in my Gantt view. The results:

flaw2.5

That’s it for now. I hope you liked reading the post, leave a comment below and I’ll be sure to reply. Keep an eye open for my next flaw: Lack of structure  (Work Breakdown Structure)

This article was originally published on Erik van Hurck’s website, The Project Corner. You can visit his website for more helpful tips.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

7 Incorrect Ways to Use Microsoft Project: Capacity as Activity

This is the second article of this series highlighting common incorrect uses of Microsoft Project. The images in these posts are built using the Microsoft Project 2013 Pro edition, but this series can be useful […]

2 min read
•almost 12 years ago•Updated 3 months ago•
E
Erik van HurckAuthor
Project Management
Microsoft Project
Best Practices
Productivity
E
Erik van Hurck

Content Writer

Erik van Hurck is a Senior PPM consultant for Projectum, a western European Microsoft Partner with offices in Denmark and The Netherlands. On top of that Erik is a Microsoft MVP. As such, Erik assists enterprise customers to adopt the new Power Platform cloud solutions for Project and Portfolio Management. Beyond writing for MPUG, Erik also has a personal blog (www.theprojectcornerblog.com).

View all articles by Erik van Hurck
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

The Integrated Master Plan: Terrible Name, but a Great Idea
Articles
1 min read

The Integrated Master Plan: Terrible Name, but a Great Idea

The Integrated Master Plan uses events, accomplishments, and criteria to define objective progress before scheduling begins. Here’s what it is and why it works.

A
Anonymous
8 days ago
Read
Managing the Sands of Time: How IT Projects Reflect an Hourglass
Articles
1 min read

Managing the Sands of Time: How IT Projects Reflect an Hourglass

Discover how the hourglass metaphor reveals the way time, tasks, and momentum work together in IT project management — and why managing the flow is the key to project success.

A
Anonymous
15 days ago
Read
Your Project Online Migration Questions, Answered: Key Takeaways from Ira Brown
Articles
1 min read

Your Project Online Migration Questions, Answered: Key Takeaways from Ira Brown

Ira Brown, president of Project Widgets, breaks down the four realistic migration paths, key deadlines, and a pre-migration inventory checklist to help your organization plan ahead of the September 2026 Project Online retirement.

A
Anonymous
about 1 month ago
Read
Explore All Articles