As a consultant you come across a lot of different projects/companies/people. I’ve noticed that there are some flaws that keep popping up, regardless of the company, project or person.

In this series of articles, I would like to explain 7 of these flaws and subsequently show you how to solve each situation.

Flaw #1: Date-Related Planning

Take a close look at this Gantt table, and more specifically at the Indicators column (the blue “i” icon left to task mode):

flaw1

How did these calendars get there? There’s a good chance you used the Start and Finish columns to enter the dates for the tasks. Granted, those dates are editable, but they should not be edited by hand.

What will go wrong?

If you have a schedule like this, none of the tasks are linked. And that will produce a lot of work for you when you change a tasks duration. Have a look at what happens:

flaw2

Did you see that? I changed the duration for task 1, but now task 2 has a incorrect starting date. Let’s fix this.

Ideally there are just two dates that should be entered in any schedule –  there can be more but I’ll get to that later. These dates are the Project Start date (you can find that one in the Project information menu) and a deadline on the milestone for the finished product. That deadline is a fixed point in time that will not move and often has a external source like your manager or a client.

All other dates are derived from dependencies!

A dependency will force the start date of a task to a later date if the predecessor takes longer to finish.

flaw3

The only thing I changed between the top and bottom image was the duration. Because task 1 was linked to task 2 (start-to-finish), the second task got a different start and finish date. Great!

Now for that exception I mentioned earlier:

There are some tasks that should have a calendar (a “start no earlier than constraint” as it is officially called). These are tasks that have external predecessors. For example, you need approval of the board, and they meet only once a month. The first possible date they get together will be your constraint. Make sure you add a note to that task, that way you will know why you added that constraint.

That’s it for now, stay tuned for my next flaw: Capacity as Activity.  Leave a comment below and I’ll be sure to respond.

This article was originally published on Erik van Hurck’s website, The Project Corner. You can visit his website for more helpful tips.


Related Content

Webinars (watch for free now!):
How to Determine the Right Scheduling Approach for your Project
Digging Deeper – Learning More about Using Constraints

Articles:
7 Incorrect Ways to Use Microsoft Project: Not Using the Baseline Functionality
7 Incorrect Ways to Use Microsoft Project: Forgetting to Set a Status Date


Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Project Management
Microsoft Project
Best Practices
Productivity
E
Erik van Hurck

Content Writer

Erik van Hurck is a Senior PPM consultant for Projectum, a western European Microsoft Partner with offices in Denmark and The Netherlands. On top of that Erik is a Microsoft MVP. As such, Erik assists enterprise customers to adopt the new Power Platform cloud solutions for Project and Portfolio Management. Beyond writing for MPUG, Erik also has a personal blog (www.theprojectcornerblog.com).

View all articles by Erik van Hurck
Articles

7 Incorrect Ways to Use Microsoft Project: Date-Related Planning

As a consultant you come across a lot of different projects/companies/people. I’ve noticed that there are some flaws that keep popping up, regardless of the company, project or person. In […]

3 min read
•over 12 years ago•Updated 7 months ago•
E
Erik van HurckAuthor
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

monday.com AI Workflows Now Pause for Human Approval
Articles
1 min read

monday.com AI Workflows Now Pause for Human Approval

MPUG Editorial · August 26, 2026 · ~4 min read · Category: PM Platforms monday.com AI Workflows can now stop mid-run and wait for a person to say yes. The […]

A
Anonymous
6 days ago
Read
Ask Gemini in Google Chat: An AI Command Line Aimed Squarely at Status Chasing
Articles
1 min read

Ask Gemini in Google Chat: An AI Command Line Aimed Squarely at Status Chasing

MPUG Editorial · August 25, 2026 · ~5 min read · Category: Productivity Tech Starting August 26, 2026, Ask Gemini in Google Chat puts a single prompt box inside the place most […]

A
Anonymous
6 days ago
Read
Copilot Meeting Prep Lands in Classic Outlook for Windows
Articles
1 min read

Copilot Meeting Prep Lands in Classic Outlook for Windows

MPUG Editorial · August 24, 2026 · ~4 min read · Category: AI & Copilot Copilot meeting prep — the feature that assembles context, action items, and documents before a […]

A
Anonymous
7 days ago
Read
Explore All Articles